The Alizés program in Senegal, drawing its inspiration from this in Mauritania, is composed of the following main points :

  • To equip villages for supplying water of than 20 000 people
  • Integration of the project into the State action, 
  • Valorization of local renewables resources
  • Use of tested pump, 
  • Local manufacturing
  • Organization of the maintenance and of the equipment’s renewal.

2004 - 2008 : water and health on the riverside of Senegal

6 villages of the Senegal valley (North of Senegal, between Saint Louis and Podor) will be equiped with a pumping system including treatment of the water from  the Senegal river

  10 villages near Louga will be equiped with a wind pump or a PV pump, a storage basin and public fountains.  It is the same design than during the period 1997- 2003.

Khare_003.jpg (30950 octets)

Khare : people used the river water

click to enlarge

implantKeurMandiol2.JPG (12824 octets)

Study of the proposal near the well 
at Keur Mandiol

go up


1997-2003 period : supply drinking water to 10 000 people

From 1997  to 2003, 28 villages located in the Northwestern part of Senegal (near Louga and Saint Louis) have been equiped with pumping systems :

  • 24 villages  use a windpump installed on an existing  well  with a depth from  20 to 35 m. Each installation includes the wind pump, two water tanks of 10 m3 each, a water distribution system and a fence in order to keep clean the water point.

  • 2 villages  dispose of a solar pump.

  • 2 riverside villages  have a pumping system including treatment of the water from  the Senegal river.

To benefit from a wind pump’s installation, the village must meet the following conditions :

The water must be intended to the whole community
To satisfy the technical criteria : less than 500 inhabitants, water to less than 30 metres, be situated in the Project Area of Alizes
To participate in the investment  in giving 400 000 FCFA ( about 610 Euros)
To subscribe an annual maintenance contract by an approved firm
To save up each year on a bank account or on a giro account for the equipment's renewal.
To form a committee for the waterhole's administration
To make a voluntary request to ALIZĖS

The training to hygiene and health

A training to hygiene and health is realized to maintain the water quality,  especially during the transport and the stocking in the concession. 

 

Corvee_deau.dat.jpg (7187 octets)

Water hardship in the river
click to enlarge

 

Eolienne_de_Thiary_Loro.jpg (40773 octets)

Wind pump of Thiary Loro

 

BFTaibaNdiuoga2.JPG (19101 octets)

Water distribution system and a fence 
in order to keep clean the water point