COSTS OF INVESTMENT
<french> |
The following informations concerned Alizes 1 (1998 - 2003 program).
The planned investments on well
| A complete installation on well costs about 6400 €, to which up to 3800 € must be added for the renovation of the existing waterhole. |
Investments |
Amounts (€) |
|
1 wind pump |
2750 |
|
|
Installation’s work |
450 |
|
|
Basins 2 x 10 m³ |
2600 |
|
|
A public drinking fountain with a fence |
600 |
|
|
Total |
6400 € |
Pumping on wells : 47.4 € of investment per inhabitant (balance 2001, june)
Investments for 26 villages (24 windpumps, 2 PV pumps) are following :
| investments | number | total amount (€) | mean amount per village (€) |
| pumps | 29 | 220 441 | 7 607 |
| civil work (basins, drinking-fountain...) | 28 | 110 830 | 3 964 |
| renovation of the well | 8 | 26 831 | 3 354 |
| total for 7560 inhabitants | 358 103 | ||
| per inhabitant | 47.4 € | ||
The cost of the windpumps :
Nevertheless, many installations realized in the Kébémer and Tivaouane departments concern villages where the well has been built or renovated thanks to the American association World Vision, which is very active in that area.
Photos of some installations : click here
The pumping and water treatment station’s cost : 50 € / inhabitant
The pumping and water treatment stations, of high capacity and more complex technically, have an investment’s cost superior :
The innovant caracter of these installations and the size of the 2 villages explained the large difference between planned and real costs.
But there is not a real difference of the cost of investment per inhabitant between the two types of installation (on well or on river water).
Photos of the 2 installations : click here
More informations :
email : info(a)alizes-eole.com