1997-2003 period : supply drinking water 
to 10 000 personnes

<french>                                                                                                                     go up to welcome



The project : 33 windpumps and 3 solar pumps

From 1998 to 2001, 32 villages located in the Northwestern part of Senegal (departments of Dagana, Louga, Kebemer and Tivaouane) will be equiped with pumping systems : 

Wind pump of Thiary Loro Water hardship in the river
Eolienne_de_Thiary_Loro.jpg (40773 octets)

Corvee_deau.dat.jpg (7187 octets)

click to enlarge

go up


7 conditions to obtain a wind pump

To benefit from a wind pump’s installation, the village must meet the following conditions :

  1. The water must be intended to the whole community

  2. To satisfy the technical criteria : 

  • less than 500 inhabitants

  • water to less than 30 metres
  •  be situated in the Project Area of Alizes

Study of the proposal near the well at Keur Mandiol

implantKeurMandiol2.JPG (12824 octets)

click to enlarge

  1. To participate in the investment  in giving 400 000 FCFA (or 4000 FRF or about 610 Euros)

  2. To subscribe an annual maintenance contract by an approved firm, notably EIC (100 000 FCFA per year)

  3. To save up 125 000 FCFA each year on a bank account or on a giro account for the equipment's renewal.

  4. To form a committee for the waterhole's administration

  5. To make a voluntary request to ALIZĖS

go up


The training to hygiene and health

A training to hygiene and health is realized to maintain the water quality,  especially during the transport and the stocking in the concession.

Water distribution system and a fence 